Consultancy Work

2017-2018
S.No Title of the Project Name of the company Duration Amount
1. UPS maintenance for the entire campus Easwari Engineeering College  1year
2. Solar PV system for water pumping DV builders and contractors 1 month Rs.5000/-
2016-2017
S.No Title of the Project Name of the company Duration Amount
1. UPS maintenance for the entire campus Easwari Engineeering College 1year
2. Energy Audit Easwari Engineeering College 1year
2015-2016
S.No Title of the Project Name of the company Duration Amount
1. UPS maintenance for the entire campus Easwari Engineeering College 1year
2. Energy Audit Easwari Engineeering College 1year
2014-2015
S.No Title of the Project Name of the company Duration Amount
1. UPS maintenance for the entire campus Easwari Engineeering College 1year
2 Test whether rewinding is required for ceiling fan or not Easwari Engineeering College 1year
3. Energy Audit Easwari Engineeering College 1year
 

2013-2014

1. UPS maintenance for the entire campus Easwari Engineeering College 1year
2 Energy Audit Easwari Engineeering College 1year
2012-2013
1. Energy Audit and Energy Conservation-Easwari Engg. college Easwari Engg.college 1 year 2,00,000
2 Power Factor Correction of PMBLDC motor using buck-boost converter  

VKT Ginning Mills(P) ltd

1 year Part of MoU
3. Power Quality Improvement for Matrix converter Digilinear Control  

1 year

Part of  MoU
4 Design and Implementation of Multilevel Inverter based DFIG for hybrid renewable energy system Orbit controls and Services 1 year Part of MoU